Customer Enrollments & Drops

To assist electricity suppliers in the enrollment and termination (drop) processes, BGE has divided the information into the following categories:

A.  Initial Electricity Supplier Enrollments

B.  Customer Switching Electricity Suppliers

C.  Electricity Supplier & Non-Residential Customer Initiated Drops

D.  Customer Closing Existing BGE Account

E.  New or Transfer Customers

F.  Sample Enrollment & Drop Letters

Electricity suppliers should also familiarize themselves with Maryland's Electric Choice rules that are covered in Section 7 of the BGE Electricity Supplier Coordination Tariff.  

 

 

A. Initial Electricity Supplier Enrollments

Customer Selects Electricity Supplier

  • When a customer initiates a contract by internet, telephone, or direct mail, the electricity supplier must maintain a record of the contract in accordance with Maryland Public Service Commission rules and regulations.

  • Only one electricity supplier may serve a customer during a billing period.  Electricity suppliers are responsible for supplying 100 percent of the customer's load.

Electricity Supplier Enrollment Transaction

  • The electricity supplier must submit a valid electronic 814E-Enrollment transaction (See EDI Implementation Guidelines) to BGE.  To be effective the next scheduled meter reading date, BGE must receive the transaction by 5PM ET at least 12 days prior to the customer's next scheduled meter reading date.  If the 12th day falls on a Saturday, Sunday, or a BGE observed holiday, BGE must receive the transaction by 5PM ET on the last business day prior to the weekend or holiday to be effective on the customer's next scheduled meter reading date. 

  • It is strongly recommended that electricity suppliers do not wait until the 12th calendar day to submit their enrollment as this does not provide the electricity supplier sufficient time to verify that the enrollment was valid through the enrollment response.  BGE will not correct invalid enrollments or give any latitude to late enrollments.  In these cases, the enrollment will become effective with the customer's subsequent meter reading date. 

  • Enrollments received less than twelve (12) calendar days prior to the customer's next scheduled meter reading date will become effective on the customer's subsequent meter reading date. BGE will not accept any future dated enrollment transactions.

  • Electricity suppliers must designate which type of billing option the customer will be using in the 814E-Enrollment transaction.  These include Dual Billing, BGE Consolidated Billing or Electricity Supplier Consolidated Billing.  For more information on these billing types, see the Customer Billing & Payment section.

  • Electricity suppliers may request historical usage at the time of enrollment using the 814E-Historical Usage request (See EDI Implementation Guidelines).  BGE will provide the data, where applicable via the 867HU-Historical Usage response (See EDI Implementation Guidelines)

  • Enrollment requests for accounts with interval meters will default to detail data.  This means that the electricity supplier will receive monthly usage summarized on the 867MU-Monthly Usage transaction (See EDI Implementation Guidelines) and will have to access the interval data via the CDWeb application on this web site.

  • BGE will confirm receipt of the 814E-Enrollment request via a 997 Functional Acknowledgement transaction.

     

    BGE Enrollment Response - Confirmation or Rejection

  • Within one (1) business day, BGE will forward to the new electricity supplier an 814E-Enrollment Response transaction. The transaction will either be an acceptance of the enrollment transaction and will indicate the effective date of energy flow (scheduled meter reading date), or will reject the enrollment transaction with an appropriate rejection code.

  • If BGE reads the customer's meter up to three (3) days before the first scheduled meter reading date or up to 15 days after the first scheduled meter reading date, BGE will modify the customer's effective date with the electricity supplier to reflect the actual reading date and send an 814-C Change transaction to update the effective date.

     

    Multiple Electricity Supplier Enrollments

  • If BGE receives multiple enrollments (enrollment of the same customer from different electricity suppliers), the last transaction received before 5PM ET twelve (12) calendar days prior to the customer's next scheduled meter reading date will become effective. 

     

    Customer Enrollment Notification

  • Within two (2) business days of receiving the enrollment response from BGE, the electricity supplier must advise the customer of their enrollment status in the form of a written communication.  The content of this notification can be electricity supplier specific, but should include the scheduled meter reading date of energy flow for all successful enrollment transactions, or notification of the reason for the rejection of the enrollment transaction. 

  • Within one (1) business day of the enrollment, BGE will notify the customer when their choice of a new electricity supplier will become effective.  For non-residential customers this notification will include information advising them to contact the supplier if they feel they were enrolled in error. The notification will also include the date by which the custoner must contact the new electricity supplier to withdraw the enrollment.  (See below for samples of BGE's Enrollment Confirmation letters).

  • Transaction Error

  • If an electricity supplier submits an enrollment or drop transaction in error, an EDI transaction to correct the mistake must be submitted within five (5) business days. If BGE receives the proper EDI transaction within the five (5) business days, the customer will be returned to their enrollment status prior to the error transaction.
  • To correct an enrollment submitted in error; submit a drop with a drop reason code of EB1. To correct a drop received by the incumbent supplier, the incumbent supplier submits an enrollment with a reason code of EB2.
  • To correct a drop submitted in error, the supplier that submitted the transaction sends an enrollment with a reason code of EB1.

 

B. Customer Switching Electricity Suppliers

A customer may elect to switch licensed electricity suppliers as often as they choose to be effective with their meter read date. 

 

All of the processes and rules for customers switching to a new electricity supplier will be the same as an Initial Enrollment described above:

Drop Transaction

  • Within two (2) business days of receiving the new electricity supplier's enrollment, BGE will send an 814D-Drop transaction to notify the customer's current electricity supplier of the customer's choice of a new electricity supplier and the scheduled meter read date of the transaction.  This step will not occur if the current electricity supplier has previously submitted a drop transaction, which will become effective on or before the scheduled meter read date of the switch being processed.

 

C. Electricity Supplier & Customer Initiated Drops

Electricity Supplier Initiated Drop Transaction

  • Notification must be provided to the customer by the electricity supplier no less than twelve (12) calendar-days prior to the effective date of the termination and must include the reason for termination.

  • The electricity supplier must send an 814D-Drop transaction to BGE. A 12 calendar-day deadline prior to the next effective meter reading date has been established to notify BGE of a pending drop. Drops received after the twelve (12) calendar-day window closes will become effective with the subsequent meter reading date. 

Electricity Supplier Initiated Drop Confirmation

  • BGE will confirm the receipt of the 814D-Drop transaction by sending to the electricity supplier an 814D-Drop Response transaction to the electricity supplier within one business day of receiving the 814D-Drop transaction. The 814D-Drop Response Transaction will establish the effective date that the electricity supplier will no longer be supplying electric energy to the customer.

  • Within one (1) business day of the drop, BGE will notify the customer in writing and indicate the effective date of the drop. (See Electricity Supplier Initiated Drop Letter samples below)

  • The termination of the customer's relationship with the electricity supplier may take effect on an estimated or an actual meter reading.

Non-Residential Customer Initiated Drop

  • All non-residential customers may drop a supplier 12 calendar days prior to the next effective meter reading date. Customer initiated drops received after the twelve (12) calendar-day window will become effective with the subsequent meter reading date. 

Non-Residential Customer Initiated Drop Confirmation

  • BGE will send to the electricity supplier an 814D-Drop transaction to the electricity supplier within one business day of receiving the Drop notification from the customer. The 814D-Drop transaction will establish the effective date that the electricity supplier will no longer be supplying electric energy to the customer.

  • Within one (1) business day of the drop, BGE will notify the customer in writing and indicate the effective date of the drop. (See the Non-Residential Customer Initiated Drop Letter samples below)

Non-Residential Customer Initiated Drop Who Rescind Their Drops

  • Maryland regulations grant all non-residential customers dropping an electricity supplier a ten-day rescission period. Any non-residential customer who wishes to rescind their drop of an electricity supplier must do so by calling BGE at 410-265-4100.  The rescission must occur by the date specified in BGE's Non-Residential Customer Initiated Drop letters (see below for samples). 

D. Customer Closing Existing Account

Electricity Supplier is Notified of Closed Account

  • When BGE is notified that the customer has closed their account (This step may occur through a customer communication or other processes such as through a service denial, etc.), BGE will perform the necessary internal business process to close the account, such as securing the appropriate meter and billing information, and initiate the 814D-Drop transaction.

Drop Transaction

  • BGE will send the 814D-Drop transaction to the electricity supplier notifying them that the customer's account is being closed. The drop will be noted as a permanent drop indicating that the customer's account has been closed and final billing data is forthcoming.

  • When available, the 814D-Drop transaction will include the customer's new mailing or forwarding address.

E. New or Transfer Customers

New Customers

  • Electricity suppliers may not submit an 814E-Enrollment transaction until a new BGE account has been made active.  This means that new customers to BGE's territory will be placed on BGE's Standard Offer Service for their first billing cycle in order to accommodate the twelve (12) calendar-day enrollment window. 

 

Customers Who Transfer Addresses

  • Customers who transfer their service to another address within BGE's territory are unable to transfer their electricity supplier's relationship to their new address.  The customer must have their electricity supplier submit a new 814E-Enrollment transaction for the new address once BGE has made the account active.  The transfer of a supplier relationship also known as a "Seamless Move" is currently not available from Maryland utilities. 
  • This means that the customer who transfers to a new address will be placed on BGE's Standard Offer Service for their first billing cycle at the new address in order to accommodate the twelve (12) calendar-day enrollment window. 

  • BGE will send the 814D-Drop transaction to the electricity supplier notifying them that the customer's old account is being closed. The drop will be noted as a permanent drop indicating that the customer's account has been closed and final billing data is forthcoming.  No drop confirmation letter will go out to the customer.

Customers Who Change Account Names

  • Customers who remain at the same address but contact BGE to have the name on the BGE account changed are unable to transfer their electricity supplier's relationship to their new name.  The customer must have their electricity supplier submit a new 814E-Enrollment transaction for the new name once the new account has been made active. 

  • This means that a change name at an existing address will cause the customer to be placed on BGE's Standard Offer Service for their first billing cycle to accommodate the twelve (12) calendar-day enrollment window. 

  • BGE will send the 814D-Drop transaction to the electricity supplier notifying them that the customer's old account with the old name is being closed. The drop will be noted as a permanent drop indicating that the customer's account has been closed and final billing data is forthcoming.  No drop confirmation letter will go out to the customer.

  • The only exception to these rules is what BGE refers to as a "Change Name Record Only".  In this scenario a customer is only changing the name due to a marriage, the result of the loss of a spouse or something similar where the same parties are responsible for the bill.  In these cases, BGE is able to change the name without creating a new account and maintain the supplier relationship. BGE will send a change transaction to the supplier to provide the correct name.