|
PLC Peak Hours & Defaults
Peak Hours for Capacity Peak Load Contributions
In accordance with the PJM RAA and PJM rules and
procedures, BGE will calculate a system capacity peak load
contribution (capacity PLC) "ticket" for each electric account on an
annual basis. After the end of a summer period, PJM will identify the five highest PJM system coincident load hours that occurred on different days over the period from June 1 to September 30. The local distribution company (LDC)-specific zones will identify the actual zonal loads
associated with these five hours. Each LDC-specific zone will
reconcile these five different hours back to the one hour weather
normalized, system coincident zonal peak load obligation. The
consequent peak load contributions will be calculated as an average
over these five hours. Each account's PLC will be updated on a yearly
basis in accordance with PJM rules and procedures, with supporting
data posted on BGE's Web site. The five days and "hour ending" times
in 2007 and 2008 used to calculate the year 2008 & 2009 capacity PLCs
respectively, are as follows:
2007 DATES |
HOUR |
2008 DATES |
HOUR |
June 27 |
4 PM |
June 9 |
5 PM |
July 9 |
5 PM |
June 10 |
5 PM |
August 2 |
5 PM |
July 17 |
5 PM |
August 7 |
5 PM |
July 18 |
5 PM |
August 8 |
5 PM |
July 21 |
5 PM |
2009 Defaults for Capacity Peak Load Contributions
In addition to calculating a system capacity PLC "ticket"
for each electric account on an annual basis, BGE also determines an
average system capacity PLC for each BGE customer segment. These
averages are used as the default system capacity PLC for any electric
account that is established with BGE after the five highest system
capacity hours have occurred (see above). Each default PLC will be
updated on a yearly basis in accordance with PJM rules and procedures
and posted on BGE's Web Site. The default system capacity PLCs for
2008 & 2009 by customer segment are as follows:
SEGMENT |
DESCRIPTION |
TARIFF CODES |
DEFAULT PLC
(effective 6/1/08 - 5/31/09) |
DEFAULT PLC
(effective 6/1/09 - 5/31/10) |
R |
Residential
(non-electric heat) |
40, 41, 46 (ES) |
2.84 kW |
2.97 kW |
RH |
Residential
(electric heat) |
42, 43 |
3.25 kW |
3.21 kW |
*RL |
Residential
Time-of-Use (TOU) (non-electric heat) |
44, 47 |
4.48 kW |
4.56 kW |
*RLH |
Residential
Time-of-Use
(electric heat) |
45, 48 |
4.41 kW |
4.34 kW |
G |
General Service (< 60 kW) |
50, 52, 53 |
7.02 kW |
6.68 kW |
GS |
General Service
Time-of-Use (< 60 kW) |
55, 56 |
22.25 kW |
21.91 kW |
GL |
General Service
Large
Time-of-Use (> 60 kW) |
65-69 |
127.79 kW |
114.86 kW |
GLP |
General Service
Large
Time-of-Use (> 60 kW) |
70-73 (13kV voltage)
76-79 (34 kV voltage)
|
|
|
P |
Primary Service
Time-of-Use |
89-90 (13kV
voltage)
95-96 (34 kV voltage)
97-98 (115 kV voltage)
|
1,728.36 kW
2,287.70 kW
12,795.61 kW
|
1,678.72 kW
2,069.66 kW
14,096.18 kW
|
Peak Hours for Network Transmission Peak Load
Contribution
Each local distribution company within PJM has a network
transmission service peak load contribution requirement. To allocate
fairly the LDC's daily requirement to electricity suppliers, network transmission
service peak load contributions (transmission PLCs) are determined. In
accordance with the Open Access Transmission Tariff (OATT) and PJM
rules and procedures, BGE will calculate a transmission PLC "ticket"
for each electric account on an annual basis. For a given year, an
account's daily network transmission service PLC requirement is based
on its load at the time of the actual unrestricted peak hours that
occurred during the twelve months ending October 31 of the prior
calendar year. At the end of this 12-month period, PJM and BGE will
identify the five highest unrestricted load hours that occurred on
different days during this 12-month period. The LDC will reconcile
these five different hours back to the highest unrestricted peak load
hour that PJM has determined to be BGE's zonal peak load obligation.
The consequent peak load contributions will be calculated as an
average over these five hours. The five days and "hour ending" times
in 2007 and 2008 used to calculate the year 2008 & 2009 network
transmission PLCs respectively, are as follows:
2007 DATES |
HOUR |
2008 DATES |
HOUR |
July 9 |
6 PM |
June 9 |
6 PM |
August 2 |
5 PM |
June 10 |
5 PM |
August 7 |
5 PM |
July 17 |
5 PM |
August 8 |
5 PM |
July 18 |
4 PM |
August 25 |
5 PM |
July 21 |
6 PM |
2009 Defaults for Transmission Peak Load
Contributions
In addition to calculating a transmission PLC "ticket" for
each electric account on an annual basis, BGE also determines an
average transmission PLC for each BGE customer segment. These averages
are used as the default transmission PLC for any electric account that
is established with BGE after the five highest transmission hours have
occurred (see above). Each default PLC will be updated on a yearly
basis in accordance with PJM rules and procedures and posted on BGE's
Web Site. The default transmission PLCs for 2009 by customer segment
are as follows:
SEGMENT |
DESCRIPTION |
TARIFF CODES |
DEFAULT PLC |
R |
Residential
(non- electric heat) |
40, 41, 46 (ES) |
2.96 kW |
RH |
Residential
(electric heat) |
42, 43 |
3.18 kW |
*RL |
Residential
Time-of-Use (TOU) (non-electric heat) |
44, 47 |
4.63 kW |
*RLH |
Residential
Time-of-Use
(electric heat) |
45, 48 |
4.32 kW |
G |
General Service
(< 60 kW) |
50, 52, 53 |
6.54 kW |
GS |
General Service
Time-of-Use (< 60 kW) |
55, 56 |
21.78 kW |
GL |
General Service
Large
Time-of-Use (> 60 kW) |
65-69 |
113.90 kW |
GLP |
General Service
Large
Time-of-Use (> 60 kW) |
70-73 (13kV
voltage)
76-79 (34 kV voltage)
|
1,673.62 kW
2,061.72 kW |
P |
Primary Service
Time-of-Use |
89-90 (13kV
voltage)
95-96 (34 kV voltage)
97-98 (115 kV voltage)
|
1,673.62 kW
2,061.72 kW
14,080.27 kW |
|