|
Energy Settlement
Introduction
As a local distribution company (LDC) within the PJM
control area, BGE is required to comply with PJM procedures. BGE's
role in energy scheduling and settlement is to provide PJM with hourly
energy schedules and the settlement of hourly energy usage. On a daily
basis, BGE will submit to PJM an initial settlement of each LSE's
hourly energy usage from the previous day (known as the "day-after
settlement") and each LSE's total capacity peak load obligation and
total network transmission peak load obligation in the BGE zone. After
all meter reading schedules are completed for a billing month, BGE
will have account-specific energy values for the month in question.
BGE will submit hourly energy differences for each LSE to PJM through
the eSchedule system (known as the "60-day settlement"). Data
submitted to PJM will be available to
electricity
suppliers on the PJM Web site.
The energy market is an hourly market with associated bids
and hourly spot market prices. Each load serving entity's (LSE) hourly
energy obligation is not separately metered on the PJM power grid. At
the onset of customer choice most retail customers will not have
meters capable of registering energy usage on an hourly basis. To
enable these customers to participate in electric customer choice, a
process known as "load profiling" will be used to estimate their
hourly energy usage and aggregate the hourly usage to each LSE for the
customers served by the LSE. The load profiling methods used by BGE
are described under the
Load Profiles link on this Web site.
To facilitate customer choice, BGE has acquired Load
Vision®, a profiling, scheduling, and settlement tool used by
utilities to schedule and settle loads.
Electricity
Supplier Hourly Energy Obligation: "Day-after" Settlement
Hourly energy use by customer account is obtained and
aggregated to the
electricity
supplier level, and these
electricity
supplier hourly energy
obligations (HEO) are reported daily to PJM using PJM's eSchedules
tool. Two procedures are required to derive the
electricity
supplier HEOs. In the
first procedure, hourly loads for each customer account are obtained
from Load Vision's database and are adjusted by the appropriate loss
factors for the daily settlement period. In the second procedure,
these loads are aggregated by
electricity
supplier to obtain the
electricity
supplier HEOs,
which are then reconciled to BGE's zonal metered hourly load. These
two procedures are described in detail below. (*Note that all
procedures are performed for each hour of each settlement period. To
simplify notation, subscripts are not shown representing each hour.)
Procedure 1: Obtain Hourly Loads for Each Customer Account
In the first procedure, 24 hourly loads are obtained for
each customer account. These hourly loads are adjusted for system
losses. There are two methods for deriving the load, depending on
whether hourly interval metered data is available for the customer
account. Each of the two methods is described below.
Interval metered Data
For an interval metered account, if interval metered data is available
for the settlement day, the hourly unreconciled load for each hour is
the metered usage multiplied by the account's loss factor, where the
loss factor is equal to one plus the loss percentage. The loss
percentage assigned to the account depends on the voltage level at
which the customer account takes electric service. For more
information about loss factors, see the
BGE Loss Factors document.
Unreconciled
Load = Metered Hourly Usage x Loss Factor
|
URLj = MHUj * LFc |
|
where: |
|
URLj
is the unreconciled load for accountj |
|
MHUj
is the metered hourly usage for accountj |
|
LFc
is the loss factor for the account's voltage class |
If an account's interval meter fails to report hourly data
for a given time period, the missing interval data will be estimated
using the account's historical usage. If no meter data is available
for the settlement day, then the account's hourly load shall be
estimated using the method for non-interval metered accounts described
below. New accounts will be assigned average loads in the day-after
settlement based on the customer segment to which they belong. In the
60-day settlement, new metered customer account loads will have been
read and used for the settlement period.
Non-interval metered Data
For non-interval metered accounts (and interval metered
accounts for whom meter data is not available for the settlement day),
the hourly load is the account's loss-adjusted profiled load
multiplied by the account's usage factor. This operation is broken
down into the following series of calculation steps described below.
Step 1: Determine 24 hourly profiled loads for each profiled segment.
Step 2: Adjust the profiled load by the relevant loss factor.
Step 3: Determine each account's usage factor.
Step 4: Derive the usage-adjusted profiled load for each account.
Step 1. Determine an hourly profiled load for each account.
A
weather-adjusted, average hourly profiled load will be determined for
each account on a daily basis in accordance with BGE's load profiling
methodology. This methodology is being implemented in the Load Vision
system, which computes profiled loads using the "Hourly Weather
Sensitive" technique. See the
Load Profiles link for more
details. This technique uses a defined season and day-type structure
to run a linear regression of historical weather data on hourly load
for each customer segment. The profiles created consist of a series of
regression equations expressing the relationship between temperatures
and load for the pre-selected season, day-type and hour combinations.
The output of this regression model is the
load profile: a set
of 24 hourly loads based on hourly weather and day-type and season
combinations.
Step 2. Adjust the profiled load by the relevant loss
factor.
The hourly profiled load for each profiled segment from Step 1 is
multiplied by the relevant loss factor for the segment.
Loss-adjusted
Profile Load = Profile Load x Loss Factor
|
LPLs = PLs * LFs |
|
where: |
|
LPLs
is the loss-adjusted profiled load for profiled segments |
|
PLs
is the profiled load for profiled segment s, e.g., 1,025 |
|
LFs
is the loss factor for profiled segment s, e.g., 1.05 |
Step 3. Determine each customer account's usage factor.
The usage factor (UF) characterizes how the customer account's usage
for an account relates to the average usage for its profiled segment.
It is defined as the ratio of the account's metered usage to the
aggregate average hourly profiled loads for that account's profiled
segment, for a billing period. The billing period used is the most
recent meter read prior to the settlement day. If a new account has no
historic or billed usage, an hourly usage factor of 1.0 will be
assigned to that account. Customers in time-of-use rate classes have a
separate usage factor calculation for each time-of-use period in the
billing period.
Usage Factor =
Metered Usage x Profiled Usage
UFj = MUj / PRUj
where:
UFj
is the usage factor for accountj
MUj
is the metered usage for accountj for the billing
period
PRUjis the
profiled usage for profiled segments for the same billing period
Step 4. Derive the usage-adjusted profiled load for each
customer account.
The
usage-adjusted profiled load (i.e., unreconciled profiled load) is the
loss-adjusted profiled load from step 2 multiplied by the account
usage factor from step 3. For each account and hour:
Unreconciled
Profiled Load = Loss-Adjusted Profiled Load x Usage Factor
|
UPLj = LPLs * UFj |
|
where: |
|
UPLj
is the unreconciled profiled load for accountj |
|
LPLs
is the loss-adjusted profiled load for profiled segments |
|
UFj
is the usage factor for accountj |
Procedure 2: Reconciliation of Hourly Loads to Zonal Total
This procedure aggregates the account's hourly loads
calculated in the previous procedure and compares the sum to the
metered system load at each hour. This procedure applies to both
interval metered and non-interval metered accounts. Any resulting
difference for each hour is allocated back to all accounts
proportional to their loads' share of system energy. This procedure is
further illustrated below by a simplified hypothetical distribution
system serving two interval accounts and two profiled segments
(monthly demand and monthly non-demand). The calculations are based on
data from the following table.
|
Meter Type |
Customer
Accounts |
Aggregated
Hourly Load |
Hourly Load
Difference |
Actual
Hourly Zonal Load |
|
Interval |
1 |
1,092.0 |
33.0 |
1,125.0 |
|
Interval |
2 |
816.4 |
24.7 |
841.1 |
|
Monthly Demand |
Total |
433.3 |
13.1 |
446.4 |
|
Monthly
Non-demand |
Total |
31.5 |
1.0 |
32.5 |
|
Total |
|
2,373.2 |
71.8 |
2,445.0
|
Hourly Load
Difference = Actual Hourly Zonal Load - Aggregated Acct. Hourly Loads
|
HLD = AHZL - AHL |
|
where: |
|
HLD is the
hourly load difference |
|
AHZL is the
actual hourly zonal load |
|
AHL is the
aggregated hourly load |
When the difference is allocated back to each account's unreconciled
load, the resulting new load value for each account is called the
reconciled load. The sum of these reconciled loads for each hour for
each
electricity
supplier represents the
electricity
supplier hourly energy obligation. As an example, the
reconciled load for interval metered account 1 in the table above
would be derived as follows:
Reconciled Load
= Unreconciled Load + (Hourly Load Difference x Load Share Ratio)
|
RLj = URLj + (HLD x LSRj) |
|
where: |
|
RLj
is the reconciled load for accountj |
|
URLj
is the unreconciled load for accountj |
|
HLD is the
hourly load difference |
|
LSRj
is the load share ratio for accountj |
|
where: |
|
LSRj
= URLj / AHL as defined above |
In the day-after settlement the reconciled loads are
reported at the whole MW level and are based on weather sensitive
static load profiles. Approximately two months after the settlement
period, at the close of the meter read cycle, dynamic load profiles
are developed based on the actual load research data for the settlement
period. The day-after hourly energy obligations derived for each day
of the calendar month are then adjusted as described below.
Hourly Energy Obligation Adjustment: "60-day" Settlement
The second phase of the PJM energy settlement process
occurs after all actual monthly energy usage data have been processed
for a given calendar month in accordance with PJM guidelines.
Procedures 1 and 2, as described above, are performed again for the
60-day settlement, which occurs approximately 60 days after the close
of a calendar month. For example, data for the month of July 1-31,
2000, will be fully processed and settled on or about October 1, 2000.
The updated
electricity
supplier HEO will be calculated using the same
processing steps used to derive the original
electricity
supplier HEO, but will
use all available data collected subsequent to the day-after
settlement. As a result of the data collection and subsequent
reprocessing:
-
The
hourly profiles for non-interval metered accounts are now based on
dynamic load profiles for the actual days of the settlement period,
instead of on weather sensitive static load profiles.
-
The
actual load data for interval metered accounts are now available to
replace the average profile used in the day-after settlement.
-
The
meter reading cycle is completed for the month to be settled, so the
hourly load profiles of all these accounts can be scaled to match
known metered usage.
-
There
may be revised estimates of hourly system loads for each day of the
settlement period. If so, the reconciliation of aggregated account
loads to system totals will match a more accurate number.
BGE will generate an adjusted
electricity
supplier HEO that is compared
to the initial
electricity
supplier HEO, and will submit to PJM a calendar-month
file containing hourly
electricity
supplier HEO kWh adjustment amounts (i.e.,
adjustment amount in kWh = original
electricity
supplier HEO less updated
electricity
supplier HEO). PJM will then issue a final bill reflecting any adjustments. The
bill adjustments issued by PJM will be calculated using the locational
marginal price (LMP) for the hours adjusted. In addition to the
adjusted
electricity
supplier HEO, PJM's monthly bills to the
electricity
supplier or scheduling coordinator shall be subject to
adjustment for any errors in arithmetic, computation, meter readings
or other errors.
Any adjustments to data after the 60-day settlement must be
mutually agreed upon by all affected LSEs. BGE will then forward the
information to PJM and PJM will place the final adjustments on the
appropriate parties' bill(s). Disputes shall be resolved through the
PJM Dispute Resolution process.
|