|
Advanced
Metering Services
Effective
April
1, 2002, advanced metering will be made available to all customers,
at their option, through a separate fee schedule in
Rider 23 - Advanced Meter Services of the
BGE Retail Electric Service Tariff. The
electricity supplier or customer must contact BGE and apply to BGE for an
advanced meter. BGE will install an advanced meter within 30 days of
the technical specifications (including telephone communications
requirements) being met by the applicant, either the
electricity
supplier or the customer.
An "advanced meter" is any meter that goes beyond Baseline
Metering Services. At a minimum an advanced meter is a solid
state meter that measures energy quantities (kWh and kVAh**)
in fifteen-minute intervals that are collected via telecommunications
technology. An advanced meter may be leased from BGE for a monthly fee
as noted in the Rider 23 - Advanced Meter Services of the
BGE Retail Electric Service Tariff. In this case,
the meter will be provided, installed and maintained by BGE.
**
With the selection
of Advanced Metering,
Rider 11 - Measured Demand of the Retail Electric
Service Tariff, demand billing based on the larger value:
90% of kVA or actual kW may be implemented.
If the
electricity
supplier or customer wishes to provide the meter to be
installed and maintained by BGE, it must, as a minimum, meet the
following technical requirements, as would an advanced meter provided
by BGE.
Advanced Meter Technical Specifications
The Electric Choice and Competition Act provides that the
transition to electric customer choice will, among other things, be
orderly, maintain electric system reliability, and be fair to
customers, investors, electric companies, and
electricity
suppliers. Technical specifications for advanced metering are
necessary to ensure the collection of accurate usage and demand data,
thereby supporting a fair and orderly transition.
1. Certification Requirements
The meter must
meet the requirements set out by
COMAR
in Section 20.50.02.02 for an electric billing device. BGE must have
copies of all raw and summary test data for any meter that is to be
used as a billing device. BGE has test results for approved meters
listed below. Test results must be provided for any meters not on
this list.
Recommended Meter: General
Electric
Approved Meter Alternatives
ABB Alpha Power Plus
Schlumberger Vectron
Siemens Quad 4+ / MAXsys 2510
Siemens S4-RXR
2. Data Measurement/Display/Recording Requirements
-
The meter must
measure and display cumulative kWh delivered.
-
The meter must
measure and display total kVAh delivered (Leading + Lagging kVars).
-
The meter must
record kWh delivered and total kVAh in 15-minute intervals for a
minimum of 45 days.
-
Channel 1 of the
meter must be programmed for kWh delivered and Channel 2 of the
meter must be programmed as total kVAh.
-
The following
displays are a minimum for the normal display sequence of a meter:
kWh delivered, total kVAh, instantaneous kW, instantaneous kVA,
power factor, kW peak, kVA peak, date and time, program ID, and
display segment test.
3. Communications Requirements
-
Meter
Communications Requirements
a.
The meter must have an internal modem with a minimum 1200-baud data
rate.
b.
The meter must have a 9600-baud optical port.
-
Telephone
Communications Requirements
a.
The customer/electricity supplier must provide a dedicated Dial In Dial Out
(DIDO) phone line within 3 feet of the meter location.
b.
The phone line must be operational under normal conditions at all
times (7 days per week, 24 hours per day).
c.
A data compatible cellular phone is an allowable option to the DIDO
phone line. BGE must be consulted for specific requirements and
approved vendors. BGE will also provide this device for a monthly fee
as noted in Rider 23 - Advanced Meter Services of the
BGE Retail Electric Service Tariff.
4. Data Interface Requirements
-
The meter must be compatible with the Utility Translation System's
MV-90 Translation Software.
-
The meter must be compatible with the latest version of the SAIC,
Enerlink meter reading and analysis software.
5. BGE Operational Requirements
-
BGE
must be provided with electronic copies of all non-standard meter
programs.
-
BGE
must be provided with a licensed copy of all non-standard
manufacturers programming software.
-
BGE
must have sole restricted access and control of all billing parameters
(Meter Time, Demand Resets, Register Resets, etc.).
-
BGE
must set and retain control of all meter passwords.
-
BGE or
its representative must perform all meter programming and maintenance.
-
Customers and
electricity
suppliers may have read only access to the billing meter and
must request this access from BGE. Additional fees may be required to
support required software licenses and additional communication costs.
|